Oct 03-09: A visited to Victoria Park Station to see where construction is for upgrading the station as well the building of the new bus terminal. We can see the new stair on the north side have been pour and strip. The new windows on the north side at platform level have been installed. Work has start on the new trim work. The new sidewalk on the west side of Victoria Park is been pour and should be finish by Oct 10. The form work is been strip from the new roof for the bus bay as the concrete has been pour. Still a section to be done to the south yet. The last of the retaining wall is been built to the street on the south end. Some back filling has started by the new stairs to the upper level.